STANDARD OPERATION PROCEDURE
- First ram bottom side, bolster plate top side should be cleaned.
- The flywheel of ram and die kushion pin is adjusted to fit comfortably with the tool.
- First top side of the bolt should be tightened.
- Then the screw rod is adjusted with the tool.
- Knockout rod and die kushion pin is adjusted to fit comfortably with the tool.
- Atlast, top side and bottom side bolt is tightened after checking the bolsterslot,ram slot, and tool slot are arranged properly.
- Then the tool should be cleaned and inserted.
- The locknut of the ram is tightened.
- Then the bottom side bolt should be tightened.
- Then the screw rod is tightened.
- After setting, first five work pieces are inspected. If the inspection is not ok then resetting will be done
- Machine bed is cleaned when the shift is going o be closed.